The onboard computer for the Ramses asteroid mission has been switched on together with connected systems for the first time. This marks a step by the assembly team towards the planned launch in 2028, needed to rendezvous with the asteroid Apophis around its flyby of Earth.
AI translation of the original article. Independent human translation review is pending. Read the original
Review information is loading.
Prime contractor OHB Italia has switched on Ramses’ onboard computer together with its connected subsystems for the first time in Milan. The European Space Agency ESA reported this on 23 September. Ramses is a joint mission by ESA and the Japanese space agency JAXA to the asteroid Apophis. [1]
The components had previously been tested individually. Engineers could now check for the first time how they work together within the spacecraft, chief engineer Ingo Gerth explains. Through the onboard computer, they can send commands to systems including data storage and the power supply.
According to the project team, this first test confirms that the connected systems work together as intended. This does not yet mean that Ramses is fully assembled or ready for flight: the switch-on concerns the module containing the main electronics. ESA provides no quantitative test results. [1]
Development is under time pressure. According to ESA, Ramses must be launched in spring 2028 to rendezvous with Apophis around its flyby of Earth on 13 April 2029. The planned period between contract signing and launch is less than three and a half years.
To save time, two parts of Ramses are being built simultaneously. While OHB Italia works on the electronics module, ArianeGroup is building the propulsion module in Lampoldshausen, Germany.
ESA plans to join the two modules in spring 2027 at the ESTEC test centre in Noordwijk. The pre-flight testing phase is then due to begin. The programme includes a thermal vacuum test, during which the complete spacecraft will be operated continuously for two to three weeks, and an accelerated simulation of the entire mission. These tests have yet to take place. [1]
According to the schedule, Ramses and two small accompanying CubeSats are due to launch in spring 2028 on a Japanese H-3 rocket. ESA has not yet given a precise launch date.
1 listed sources · explore evidence, limitations and provenance.
Sign in to give this article a thumbs up or down.
Private test discussion. Comments are readers’ views and are not yet automatically fact-checked. Editing is available for 60 seconds after posting.
Sign in with a confirmed reader account and choose a username to read comments and participate.
Sorting applies to top-level comments; replies remain oldest first. New comments and likes can change the order. Refresh for the current ranking.
Loading comments…